Some Important Questions

Question

Write the Risk Assessment Process

The Risk Assessment Process involves several key steps:

  1. Establish Context: Define the risk team, roles, responsibilities, timeline, and budget for development.

  2. Identify Risks: Research industry resources, conduct historical review, assess current state, brainstorm potential risks, and record all identified risks in a risk register.

  3. Analyze and Evaluate Risks: Assign probability and impact, analyze and evaluate risks, prioritize and decide on treatment responses.

  4. Develop Risk Strategies: Create a plan, establish risk tolerance levels, develop risk treatment tactical responses, and key risk indicators.

  5. Monitor and Review: Record risk strategies in the register, monitor and review the results of risk treatment.

Question

write a short note on risk register

A risk register, also known as a risk log, is a document used in project management and risk management to identify potential risks in a project or within an organization. It serves as a central repository for all risks identified, allowing for the documentation, analysis, and management of risks throughout the lifecycle of a project or a business operation.

Here's what a typical risk register contains:

  1. Risk Category: This groups the risk according to the area of the project or business it affects, such as strategic, operational, financial, compliance, or reputational risk.

  2. Risk Description: A detailed explanation of the risk and its potential effects.

  3. Risk Owner: The individual or party responsible for managing the risk and implementing mitigation strategies.

  4. Cause: The source or event that could trigger the risk.

  5. Effect: The potential impact on the project or business if the risk materializes.

  6. Probability: The likelihood of the risk occurring, often rated on a scale (e.g., high, medium, low).

  7. Impact: The severity of the outcome if the risk materializes, also often rated on a scale (e.g., high, medium, low).

  8. Mitigation Strategy/Response Plan: The actions or plans to manage, reduce, or eliminate the risk.

  9. Key Risk Indicators (KRIs): Metrics and indicators used to measure and monitor the risk's likelihood and impact.

  10. Status: Current status of the risk (active, monitoring, closed).

Review Dates: The schedule for reviewing the status of the risk and the effectiveness of the response plan.

The risk register is a dynamic tool that is regularly updated as new risks are identified, and as existing risks change or are resolved. It's a crucial part of the risk management process as it provides a systematic approach to identifying, quantifying, and managing risk.

Question

Frame the managing risk based on iso 31000

The management of risk based on ISO 31000 involves several key components:

  1. Mandate and Commitment: Risk management begins with the commitment of management and governance bodies to establish an effective risk framework.

  2. Design of Framework: This includes defining the organization's context, establishing a risk management policy, and embedding risk management into the organization's processes.

  3. Implementation of Risk Management: The framework is implemented, and the risk management process is put into action.

  4. Monitoring and Review: Regular monitoring and review of the framework to ensure its effectiveness and relevance.

  5. Improvement of Framework: Continuous improvement of the framework based on the findings from monitoring and review processes.

The ISO 31000 framework provides a structured approach to identifying, assessing, and treating risks, with the goal of enabling organizations to proactively manage potential threats and opportunities.

🎶